The project is looking great.

Is that the breaker panel hanging by a thread in those last two pics?

edit: Vicor rocks!

The breaker panel is hanging by the wiring lol. I need to replace the partition it is attached to and I need to rewire at least half the place. I have one outlet and two lights rigged for power atm.

Just finished up closing the exterior yesterday, and the watershield stuff does rock, and the windows are caulked with polyurethane caulk ^.^ I tested them with a hose, no visible leakes.

Now just to do the rough wire/plumbing, insulate, and drywall, which is 3-4 days labor max. Then the interior walls are -done-. Then floor which will totally take 1 day. Then siding, soffits, trim. I am looking at 3 weeks~ to completion.
 
Just finished up closing the exterior yesterday, and the watershield stuff does rock, and the windows are caulked with polyurethane caulk ^.^ I tested them with a hose, no visible leakes.

.

I have all of my new windows slathered with the Vicor. The siding could be ripped off in a hurricane but that stuff would still be there.

Kind of like cockroaches after a nuclear blast! :fly: